NEW QUESTION # 16
Which of the following is NOT an interest into which each DSDM role is grouped?
- A. Management
- B. Maintenance
- C. Business
- D. Solution/Technical
Answer: A
NEW QUESTION # 17
Which plain defined by DSDM, has a planning horizon that includes the end of a project?
- A. Delivery
- B. Detailed
- C. Timebox
- D. High-Level
Answer: A
NEW QUESTION # 18
When is a Timebox Plan updated?
- A. Each time a Timebox is completed
- B. At the Daily Start-ups
- C. As needed by the Project Manager
- D. At Timebox Kick-ups
Answer: A
NEW QUESTION # 19
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.
- A. Viewed in light of the overriding project goal
- B. Made collaboratively
- C. The responsibility of the Business Sponsor
- D. Share between all of the project roles
Answer: B
NEW QUESTION # 20
How does the Post-Project phase add value to a project?
- A. Checks how well the expected business benefits have been met
- B. Iteratively explores the low- level detail of the requirements
- C. Brigs a baseline of the Evolving Solution into operational use
- D. Define how the operation of the solution will be managed
Answer: A
NEW QUESTION # 21
Which statement about change is correct for DSDM?
- A. Project operate with a changing world
- B. Avoid change whenever possible
- C. Change is inevitable and males estimating very difficult
- D. Change is a symptom of an inability to define requirements properly
Answer: A
NEW QUESTION # 22
What DSDM product is identified as a governance product because if may be used for purposes such as prioritization of a project within a portfolio?
- A. Prioritized Requirements List
- B. Terms of Reference
- C. Business Case
- D. Feasibility Assessment
Answer: B
NEW QUESTION # 23
During what phase should a baseline of the Evolving Solution be put into operational use?
- A. Evolutionary Development
- B. Post-Project
- C. Foundations
- D. Deployment
Answer: D
NEW QUESTION # 24
Which purpose relates to the instrumental Success Factors?
- A. Positions DSDM projects for a successful outcome
- B. Underpins the prioritization of requirements
- C. Informs the development of the Business Case
- D. Inform the development of the Terms of Reference
Answer: C
NEW QUESTION # 25
Which statement applies to the DSDM process?
- A. DSDM projects can deliver the phases in the DSDM process in any order
- B. Can be configured and calibrated to cater for light or strong governance
- C. Provides an approach that can be used for all projects without change
- D. Does not require the elaboration of supporting products for complex projects
Answer: B
NEW QUESTION # 26
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?
- A. Workshop Facilitator
- B. Business Analyst
- C. Business Ambassador
- D. Business Visionary
Answer: A
NEW QUESTION # 27
Which of the following support the DSDM philosophy and principles?
- A. Phases, productivity, power and process
- B. People, products, phase and plans
- C. Process, people, products and practices
- D. Plans, projects, process and people
Answer: C
NEW QUESTION # 28
According to the DSDM principle 'Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?
- A. Whenever the level of solution quality is known.
- B. During evolutionary development
- C. At the start of the project
- D. When the Business Advisor is available
Answer: B
NEW QUESTION # 29
What is the MoSCoW technical used for?
- A. Ensuring a team-based approach through visual and verbal communication and collaboration.
- B. Creating a visual representation of a problem or a solution.
- C. As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.
- D. Understanding and managing priorities.
Answer: D
NEW QUESTION # 30
How are the business roles critical to the success of a DSDM project?
- A. Guide the evolution of the solution at the detailed level
- B. Make all decisions
- C. Lead Solution Developer demonstrations
- D. Provide formal progress reporting
Answer: A
NEW QUESTION # 31
What role is responsible for the delivery of the project from Foundations through to Deployment?
- A. Project manager
- B. Technical Coordinator
- C. Business Visionary
- D. Business Sponsor
Answer: A
NEW QUESTION # 32
When initially creating MoSCoW priorities, what is the primary focus?
- A. Project priorities
- B. Timebox priorities
- C. Iterative Development priorities
- D. Project increment priorities
Answer: A
NEW QUESTION # 33
When should the quality of the evolving solution first be tesed?
- A. As part of the iterative Development process
- B. At the end of each increment
- C. At the end of a project.
- D. At the end of a Timebox
Answer: A
NEW QUESTION # 34
During what phase should the strategy for Iterative Development be considered?
- A. Evolutionary Development
- B. Foundations
- C. Pre-Project
- D. Feasibility
Answer: B
NEW QUESTION # 35
How does DSDM differ from most other Agile approaches?
- A. It focuses on the development of products
- B. It focuses on the entire project lifecycle
- C. It focuses on the delivery of products
- D. It focuses on the collaborative working of teams
Answer: B