24/7 the whole year after-sale service
We have a group of dedicated staff who is aiming to offer considerable service for customers 24/7 the whole year. We are not only assured about the quality of our ISO-21502-Lead-Project-Manager exam guide: PECB ISO 21502 Lead Project Manager Exam, but be confident about the after-sale service as well. So we have been trying with a will to strengthen our ability to help you as soon as possible. Our ISO-21502-Lead-Project-Manager real dumps speak louder than words, if you have other problem or advice about our ISO-21502-Lead-Project-Manager test engine materials, don't hesitate to contact with us any time and we will solve them for you with respect and great manner as soon as possible. At latest, you can go through the exam absolutely after purchasing and studying our ISO-21502-Lead-Project-Manager exam guide: PECB ISO 21502 Lead Project Manager Exam.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Perfect products made by Professional group
We have always been attempting to assist users to get satisfying passing score all the time by compiling reliable ISO-21502-Lead-Project-Manager Exam Guide: PECB ISO 21502 Lead Project Manager Exam. That is the reason why we invited a group of professional experts who dedicate to the most effective and accurate ISO-21502-Lead-Project-Manager exam guide: PECB ISO 21502 Lead Project Manager Exam for you. To sort out the most useful and brand-new contents, they have been keeping close eye on trend of the time in related area, so you will never be disappointed about our ISO-21502-Lead-Project-Manager test engine questions once you make your order. And you can absolutely get the desirable outcomes. They not only compile the most effective ISO-21502-Lead-Project-Manager real dumps for you, but update the contents with the development of society in related area, and we will send the new content about the PECB ISO-21502-Lead-Project-Manager exam to you for one year freely after purchase.
Our exam materials can be trusted & reliable
We have been compiling the important knowledge & latest information into the ISO-21502-Lead-Project-Manager exam guide: PECB ISO 21502 Lead Project Manager Exam over 8 years and the products have been very effective for many people. So it is a best way for you to hold more knowledge of the ISO-21502-Lead-Project-Manager real dumps materials. Owing to our special & accurate information channel and experienced education experts, our ISO-21502-Lead-Project-Manager dumps guide get high passing rate and can be trusted. By spending up to 20 or more hours on our ISO-21502-Lead-Project-Manager latest exam torrent questions, you can clear exam surely. About the updated versions, we will send them to you instantly within one year, so be careful with your mailbox.
Finally, the ISO-21502-Lead-Project-Manager exam guide: PECB ISO 21502 Lead Project Manager Exam will bring you closer to fulfill the challenge of living and working. Our exam materials are aiming to allay your worry about exam. Our ISO-21502-Lead-Project-Manager real dumps not only help you master questions and answers of the real test but also keep you easy mood to face your test. We can totally be trusted. Good luck!
Currently, so many different kinds of exam preparation materials about the PECB exam flooded into the market which makes examinees feel confused about how to choose, and you may be one of them. As our ISO-21502-Lead-Project-Manager Exam Guide: PECB ISO 21502 Lead Project Manager Exam are always commented as high quality & high pass-rate, we guarantee that our ISO-21502-Lead-Project-Manager Test Engine is a nice choice for you and ISO-21502-Lead-Project-Manager Real Dumps will help you pass exam surely. So it is really a wise action to choose our products. Now please take a thorough look about the features of the ISO-21502-Lead-Project-Manager real dumps as follow and you will trust our products, so does our services.

PECB ISO-21502-Lead-Project-Manager Exam Syllabus Topics:
| Section | Weight | Objectives |
| Topic 1: Fundamental Principles and Concepts of Project Management | 28.75% | - Project Life Cycle and Phases
- Overview of ISO 21502 Standard
- Project, Program and Portfolio Distinctions
- Project Governance and Stakeholders
- Project Management Principles
|
| Topic 2: Individual Management Practices for a Project | 36.25% | - Planning and Estimating Activities
- Closing and Evaluating the Project
- Initiating and Starting a Project
- Directing and Executing Work
- Monitoring and Controlling Performance
|
| Topic 3: Integrated Project Management Practices | 35% | - Project Organization and Roles
- Project Communication and Reporting
- Project Integration Management
- Project Risk and Opportunity Management
- Project Scope and Planning
|
PECB ISO 21502 Lead Project Manager Sample Questions:
1. According to ISO 21502, what should the process of controlling risks involve?
A) Developing options and actions to enhance opportunities and reduce threats to the project
B) Ensuring that responses to negative risks minimize disruption to the project while responses to positive risks maximize beneficial impact
C) Determining common causes which can help develop priorities for treating risks
2. Scenario:
Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in- flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.
Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.
Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.
While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.
A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.
Question:
According to scenario 3, the business case was updated to reflect the changes made regarding the project delivery. Is this acceptable?
A) Yes, the business case can be updated to reflect changes on the project delivery, but not to reflect changes on other aspects of the project
B) No, the business case can be updated only during pre-project activities
C) Yes, the business case should be updated to reflect changes in the project's context
3. Scenario:
Tricko is a clothing manufacturer headquartered in Milano, Italy. The company was founded in 2010 by Mario, a famous Italian fashion designer. Over the last few years, the company has seen immense growth and now has a chain of stores across multiple European cities. Following industry trends, the top management of Tricko concluded that the company should establish an online store. As such, they required Lily, an experienced IT engineer, to develop a brief for this potential project. After several meetings and discussions, the top management approved the project brief and assigned Lily as the project manager. For this project, she was instructed to use the guidelines of ISO 21502 on project management.
Lily initiated the project by mobilizing the project team, which included four web developers, two network engineers, and one systems analyst. In order to ensure that every team member is fully aware of their roles and responsibilities, Lily developed team performance domains which would link each project activity with the individuals responsible for undertaking it. She explained to the team members that it is important to clearly understand their roles and responsibilities, considering that the team composition cannot be reassessed or revised once the project plan is authorized to be executed. In addition, Lily defined in a document the project's contribution to the overall objectives of Tricko, which reflected the relevant project requirements and their associated acceptance criteria.
Following that, Lily worked with the project team to discuss project costs. She suggested the team initially establish cost estimates only for the first phase of the project and then for the entire project. In addition, she required cost estimates to be expressed in currency valuations and in labor hours. One of the network engineers suggested that each team member should provide an estimate, and then the team should reach an agreement for a joint estimate. On the other hand, one of the developers suggested establishing an estimate for the costs after the closure of the project, such as advertising and promotion costs. Lily agreed with their suggestions and asked them to provide a total estimate as soon as possible.
Based on the total estimate provided by the project team, Lily developed the project budget and created a list of project activities, divided them into smaller items, and assigned a budget for each item.
Question:
Based on scenario 5, which estimation method for project cost did the network engineer propose?
A) Wideband Delphi estimating
B) Single-point estimating
C) Parametric estimating
4. Which of the following statements describes a project termination by extinction?
A) The project is closed due to the integration of project outputs to the operations of the parent organization
B) The project is closed due to its failure or successful completion
C) The project is closed with the intention to resume at another time in the future
5. Scenario:
Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in- flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.
Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.
Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.
While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.
A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.
Question:
Scenario 3 indicates that Michaele authorized the project initiation. Is this acceptable?
A) Yes, the project initiation should be approved by the sponsoring organization
B) No, the project initiation should be approved by the project manager in consultation with work package leaders
C) No, the project initiation should be approved by the project manager
Solutions:
Question # 1 Answer: B | Question # 2 Answer: C | Question # 3 Answer: A | Question # 4 Answer: B | Question # 5 Answer: A |